The mall’s handbook is the rule. Two published ones are not every mall

A mall fit-out is the landlord’s permit plus the statutory ones. CapitaLand’s July 2024 checklist and the Heartbeat@Bedok guide publish different hours and different hoarding rules. They are examples, not a national code. There is no standard fit-out period and no corridor width on this page.

4.9

trusted by 500+

The shopfronts of Heartland Mall in Singapore

Photo: Angcr, CC BY 3.0, via Wikimedia Commons. Heartland Mall. It is not a tenant handbook and not a job carried out by HomeySG.

HDB licensed renovation contractor badge
Warranty satisfaction badge
Singapore service badge

How it works

  1. 1

    Read the clause that applies to your premises before you book a fitting.

  2. 2

    Match a printed band only when the photo is that fitting. Otherwise the answer is quote on inspection.

  3. 3

    Name the licensed party where the work is regulated. We do not sign the licence.

  4. 4

    Confirm the scope in writing. A guide is not an invoice.

What this job is

Last updated 31 October 2026.

1. Read that mall’s handbook 2. Form or permit on the hoarding 3. QP where fire safety changes 4. Trade only after the certificate
Lease, landlord permit, then the authorities

“Mall tenant fit-out” returns interior-design galleries and, sometimes, a question about tenant rights or fair wear. The operational document is duller. It is the landlord’s fitting-out checklist: a permit displayed at the hoarding, drawings at a stated scale, insurance, a hoarding specification, and a list of nights when hacking is allowed. Two of those documents are public. CapitaLand’s Fitting Out Work Checklist and Guidelines for the CG welcome kit is dated July 2024. A second CapitaLand file for 21 Collyer Quay carries the same hours table. The Heartbeat@Bedok tenant fit-out guide, version 0.4.2, is a different landlord, Sport Singapore’s building, with different clock times. If your unit is in neither, neither document binds you. Ask your tenant service centre for the current book. Landlords reserve the right to change it.

People ask what fitting-out work is, what is included, how long a fit-out takes, and what a fit-out period is. Fitting-out, in these checklists, is the tenant’s work to make the bare unit tradable: walls, services, finishes, and the fire protection the unit must not break. What is included is the lease and the handbook, not a national list. A fit-out period is whatever the letter of offer states. We do not publish a duration. A contractor who promises “four weeks because that is standard” is inventing a standard. The reinstatement page prices a small strip-out. It does not price a mall opening date.

People also ask about corridor width. We do not publish one. The approved building plan and the Fire Code set circulation for that building. A blog’s “standard mall corridor” is not a measurement you can build to. Fair wear and tear, and eviction, are the lease and the who-pays guide. We do not advise tenants to call the police, and we do not interpret a deposit.

Curtains, blinds and roller shades are not part of this booking. A roller shutter is a different product and stays on the shutter page.

How the work is done

CapitaLand’s checklist, for the buildings it covers, requires the tenant to get authority approvals and to give the tenant service centre a copy. The landlord’s own permission is Form F3, Permit for Carrying Out Building Fitting Out Work, endorsed and displayed at the entrance. Hacking, demolition and drilling are limited to the permitted hours in that checklist: Monday to Friday, 7.00 pm to 7.00 am the next day; Saturday, 2.00 pm to 9.00 am the next day; Sunday and public holiday, 9.00 am to 5.00 pm. Minor works may happen in ordinary hours if they are not noisy, dusty, smelly or in the way. The centre can stop the work. If you work outside those hours, the checklist says attendance and standby fees, if any, are the tenant’s, and it points at a value-added-services schedule. We did not copy a dollar from that schedule. If your centre charges one, it is their invoice.

Hoarding, in the same checklist, goes up before fitting-out. The design comes from the centre. It runs floor to ceiling, joints plastered and painted, new gypsum sheets, two coats of lily-white emulsion. The outgoing tenant lets the incoming tenant put graphics on it, or pays for the landlord’s interim graphics. Heartbeat@Bedok is different and should be quoted as different: full-height gypsum or a white polykem finish, set within or 600 mm outside the lease line, installed between 8.00 am and 10.00 pm, no noisy work after 10 pm, and the hoarding stays after reinstatement unless the managing agent agrees otherwise. Using CapitaLand’s night window at Heartbeat, or Heartbeat’s 600 mm line at a CapitaLand mall, is how a hoarding gets torn down at the tenant’s cost.

Insurance is a condition, not a slogan. CapitaLand’s checklist wants copies of the policies, with insurers licensed in Singapore and acceptable to the landlord, before work starts. The handbook names the policies it wants. Send those copies. Do not ask a handyman visit to double as the contractor’s all-risk cover. Our mall overnight row, S$380 to S$650, is permit-to-work admin and one hardware fix when the centre requires the night slot. It is not a fit-out contract, not a hoarding, and not the centre’s standby fee.

What you should see at the endWhat a sloppy visit leavesWhy it matters
The current handbook for that centre is on the tableA different landlord’s PDF used as the ruleThe hours and the hoarding line will be wrong
Form F3 or the equivalent permit is on the hoardingWork starting because the keys were collectedThe centre can stop you
Hoarding is the specified board, floor to ceiling, in the specified colourA banner tied to mall railingsDust in the corridor is the complaint that stops the job
Fire safety works have a qualified person and a certificate before tradingOpening on a temporary permit that was never closed outSCDF treats trading without the certificate as an offence

How to scope it

Split the fit-out from the punch list. The fit-out is the handbook, the qualified person and the authorities. The punch list after opening is the shop touch-up page: showcase hardware, a shutter, a silicone joint. A single dead lamp after opening is the lighting page. Do not hire a fit-out main contractor to change a hinge, and do not hire a handyman to submit fire-safety plans.

Sprinkler heads are the usual trap. CapitaLand’s checklist points additions and alterations at the centre’s form and at the code it names on that page. SCDF’s plan-approval page lists changes to sprinklers, detectors, exit signs and fire doors as fire safety works that a qualified person submits before the work. Moving a head to suit a ceiling feature is that submission. It is not a night-shift extra.

What you seeWhat to photographStop
You have a handbook from a different mallThe centre’s own current fileStop using the other hours
Hacking is planned for a weekday afternoonThat centre’s permitted hoursCapitaLand’s weekday hacking window is overnight
The hoarding is mesh or a bannerThe specified board and paintThe centre can rebuild it at your cost
You want to trade before the fire certificateThe FSC or a real TFPA landlord letter is not the certificate

Which job you actually have

Match the building, then match the trade.

SituationUse thisLeave this alone
CapitaLand CG or the same hours tableThat checklist’s nights for hackingNot a heartland shop’s Saturday morning
Heartbeat@Bedok8am to 10pm for the hoarding install, no noisy work after 10pmNot CapitaLand’s overnight window
One hardware fix the mall will only allow at nightS$380 to S$650Not a fit-out contract
Sprinkler, exit sign, fire door, or a change of useQualified person and SCDFNot a handyman
Lease-end strip of about 300 sq ftS$3,000 to S$7,500Plus whatever that mall’s reinstatement book adds
A fit-out period or a corridor widthThe lease and the approved planNot a number from this page

Questions a shop should ask

Questions a shop should ask

Ask the centre, then ask the contractor to repeat the answer.

  1. Which handbook is current for this centre, and what date is on it?
  2. Where is the endorsed fit-out permit, and is it on the hoarding?
  3. What are the hours for hacking, and what are the hours for quiet work?
  4. What is the hoarding specification, including colour and the lease line?
  5. Which insurance copies does the centre want before day one?
  6. Which fire safety works need a qualified person?
  7. Is a Fire Safety Certificate required before trading, or is a Temporary Fire Permit even available?
  8. Is a standby fee the centre’s invoice or a guess?

A managed mall, a heartland centre, or an HDB shop that is not a mall

Heartland Mall in the photograph is not automatically on CapitaLand’s clock.

QuestionManaged mallHDB shop without a mall handbookStrata shop in a mixed development
Who sets the hoursThat centre’s checklistHDB’s shop guideThe MCST plus the landlord
HoardingAs the handbook draws itThe shop guide’s housekeeping, not lily-white gypsum by defaultWhoever the by-law names
Fire certificateSCDF if the works are fire safety worksSame Act, smaller scope if you did not do those worksSame
Our night rowOnly when that mall requires the slotNot charged by habitOnly if a permit-to-work is actually required

The fire certificate is not the landlord’s letter

SCDF’s page on the Fire Safety Certificate says owners and their qualified persons obtain the certificate before the premises are used or occupied, after the fire safety works are complete. Trading without it is an offence under the Fire Safety Act 1993. A Temporary Fire Permit exists only when the works are satisfactorily complete with very minor items outstanding, and the certificate still has to follow. You apply after plan approval and after a registered inspector’s inspection certificate. The landlord’s “you may open” email is not that certificate.

The plan-approval page lists what counts as fire safety works: changes to hose reels, alarms, sprinklers and exit signs; layout changes that affect escape or compartmentation, including replacing fire doors; works involving air-conditioning or ventilation, or LPG for non-residential use; and a change of use that affects fire safety, such as a shop becoming an eating establishment. Plans are by a qualified person. Minor additions have a separate lodgement path. CapitaLand’s checklist draws both flowcharts, the certificate path and the minor-works acknowledgement. Follow the one your qualified person says applies. Do not pick the shorter flowchart because the programme is late.

A handyman punch list after the certificate is a different week. Hinges, a silicone joint, a shutter limit and a patch are the touch-up page. They do not reopen the fire strategy. If a patch would cover a detector or a sprinkler, stop. That is no longer a patch.

Rules that apply

CapitaLand’s checklist and the Heartbeat@Bedok guide are cited as those landlords’ documents. They are not blended into one “Singapore mall rule”. SCDF’s certificate and plan-approval pages are the statutory layer that sits underneath every landlord. BCA’s building-work question is separate again: a fit-out that is building work needs the building approval even when the mall has said yes.

MOM’s workplace duties still apply to a fit-out site. A hoarding is not a substitute for a risk assessment. We do not write the centre’s permit and we do not insure the main contract. The overnight hardware row remains the narrow product on the mall page.

Official pages

Homey Furnishing Pte. Ltd. (ACRA UEN 202018148K), 27 Mandai Estate, #06-10 Innovation Place, Singapore 729931, invoices the permit-exempt visit. V On Construction Pte. Ltd. (ACRA UEN 201611708H), on the HDB Directory of Renovation Contractors, invoices hacking, a new layout, and an HDB renovation permit. Homey Furnishing is not a property agency, not a CEA practice, and not a vector-control operator.

How you're charged

How you're charged

A job that already has a sentence on HomeySG uses that sentence. The hour is not added on top of a band unless the written scope says so. There is no fuel surcharge and no published night premium except the mall overnight row. A shop does not inherit a flat’s price just because the fitting looks similar.

ChargeWhat it covers2026
Per hourPermit-exempt handyman time after a priced task, if the scope says soS$45/hr
Minimum, one taskOne permit-exempt task on one visitS$55
Mall overnightPermit-to-work admin and one hardware fix when the mall requires the night slotS$380 to S$650
A matching catalogue rowThe photo matches a row already printedThat row
A gondola run, a cassette aircon, a full shop repaint, a camera, a floor trap sizeNo catalogue row for that productquote on inspection

This guide does not price a fit-out. The overnight row is only the published hardware slot. Reinstatement bands are only the scopes already printed. A centre’s standby fee is the centre’s bill.

Ways to keep the bill smaller

Ways to keep the bill smaller

  • Get the handbook before you hire. Redrawing a hoarding is pure waste.
  • Put sprinkler and exit-sign changes in the qualified person’s first submission, not in week six.
  • Do not open on a landlord email. The certificate is the document that lets you trade.
  • Keep the punch list off the main contract. A hinge does not need a fit-out preliminaries bill.

WhatsApp the photos to +65 8561 0630.

Price, or quote on inspection

Two published repair figures are easy to confuse with a fit-out. They are not one.

Anything not in that table is quote on inspection.

Scope already published2026 band in the repoWhere it lives
Mall overnight, one hardware fix and the permit adminS$380 to S$650Mall page, only if the centre requires it
Micro-reinstatementS$1,800 to S$4,500Reinstatement
About 300 sq ft strip-outS$3,000 to S$7,500Reinstatement
Showcase hardwareS$250 to S$550Mall page
A fit-out period, a corridor width, a standby feequote on inspectionThe lease or the centre. Not this site

WhatsApp the photos to +65 8561 0630. The reply uses a band already printed on HomeySG, or it says quote on inspection.

The shopfronts of Heartland Mall in Singapore
Heartland Mall. Its house rules are not CapitaLand’s, and neither is a pricePhoto: Angcr, CC BY 3.0, via Wikimedia Commons. Heartland Mall. It is not a tenant handbook and not a job carried out by HomeySG.

Related pages

Frequently Asked Questions

What is fitting out work?

In the published mall checklists it is the tenant’s work to make the unit tradable: finishes, services, and any fire protection the unit must not break. It is not a handyman punch list, and it is not the same list in every centre.

What is included in a fit-out?

The letter of offer and that centre’s handbook. CapitaLand’s checklist includes authority approvals, Form F3, hoarding, insurance and the fire-certificate path. Another landlord will title the forms differently.

How long does a fit-out take?

No duration is published here. A fit-out period is whatever your letter of offer states. A contractor’s “standard four weeks” is not a rule.

What is a fit-out period?

It is the time the lease gives you to do the work, often before rent or before trading. Read your letter. We do not supply a default.

What is the standard corridor width for shopping malls?

None is stated on this page. The approved plan and the Fire Code for that building are the measurement. Do not build to a figure from a forum.

What are the rights of tenants in Singapore?

That is the lease, not a fit-out handbook. Who pays for repairs is the who-pays guide. We do not advise on eviction.

Can I open the shop before the fire safety certificate?

SCDF says the certificate comes before use or occupation when fire safety works were done. A Temporary Fire Permit is only for very minor outstanding items, and the certificate still has to follow. A landlord’s email is not the certificate.

Tell us what you need help with

This opens WhatsApp with your details filled in. You can attach photos there for a faster quote. See our privacy policy.

Prefer to call? +65 8561 0630